Change Orders on California Home Remodels: How They Work

Writer: Tzvia Cohen
Tzvia Cohen
Nov 14
3 min read

Almost every remodel changes a little once work begins. You pick a different tile, the inspector asks for an extra item, or opening a wall shows something nobody could see before. A change order is how those changes are priced and approved in writing before the added work is done. Here is how change orders work on a California home improvement project, and what the law requires.

What a change order is

A change order is a short written document that adds to, removes from, or changes the work in your signed contract. It states what is changing, how the price changes, and how the change affects the payment schedule or the completion date. Once both sides sign it, it becomes part of your contract.

What California law requires

California Business and Professions Code section 7159 sets the rules for home improvement contracts. For change orders, it requires that:

  • The change order is in writing and signed by the homeowner and the contractor before the work it covers begins.

  • It describes the scope of the extra work or change.

  • It states the amount added to or subtracted from the contract price.

  • It states the effect on the progress payments or the completion date.

The law also says a homeowner may not require a contractor to perform extra or change order work without written authorization, and that a change order is not enforceable against the homeowner unless it identifies the scope, the price change and the effect on payments or the completion date in writing before the work starts.

Two related rules are worth knowing. The Contractors State License Board says a written contract is required for home improvement projects over $500 in combined labor and materials. The down payment on a home improvement contract may not exceed $1,000 or 10 percent of the contract price, whichever is less.

Common reasons for a change order

  • Homeowner choices: a new layout, an added outlet or fixture, or a different finish after the contract is signed.

  • Concealed conditions: older Los Angeles homes can hide original wiring, galvanized plumbing, dry rot or framing that does not meet current code until walls or floors are opened.

  • City requirements: plan check corrections or an inspector's request for work that was not in the approved plans.

  • Material changes: a specified product is discontinued or delayed and a substitute is chosen.

How to keep changes simple

  • Choose fixtures and finishes before work starts, so fewer decisions land in the middle of the job.

  • Ask for the written price and schedule effect before approving any added work.

  • Read the description closely. It should say exactly what is being added or removed.

  • Keep a signed copy of every change order with your contract.

  • Give approvals in writing to the contractor, not verbally to the crew on site.

Written scope and change orders at AAA All Star Construction Inc

Every project we build is governed by a written contract, and only the work listed in that contract is included. Permits, city fees, engineering and city required corrections are included only when the contract says so. If we find a concealed or existing condition, we show you, document it, and price any repair in a written change order. That work, and any other added work, proceeds only after the change order is signed. Verbal requests or approvals do not change the contract. Schedules are estimates and can be affected by city review, inspections, material availability, site access and owner decisions.

Planning a remodel?

AAA All Star Construction Inc is a licensed California general contractor (CSLB #1018926) based in North Hollywood, serving Los Angeles County, the San Fernando Valley, Ventura County and Orange County. Learn more about our kitchen remodeling, bathroom remodeling and whole home remodeling services. For a free written estimate, call (844) 975 5512 or contact us.

This article is general information, not legal or engineering advice. Requirements vary by city and property; confirm them with your local building department.

 
 
 

Recent Posts

See All

Comments


Commenting on this post isn't available anymore. Contact the site owner for more info.
  • CSLB
  • Facebook
  • Yelp!
  • Pro Referral

Southern California

​

MAILING ADDRESS:

12509 Oxnard St., Suite 203,

North Hollywood, CA 91606

(844) 975 5512

​

CSLB Licensed General Contractor
#1018926 (Class A and B)

AAA All Star Construction Inc logo, licensed general contractor in North Hollywood

© 2016 AAA All Star Construction Inc, CSLB #1018926. All rights reserved.

Contact Us

Thanks for submitting!

bottom of page